Operation Guide

  1. The Periodicity trial operation is necessary for standby generator sets.
  2. Firstly finish all the inspection work before starting.
  3. Connect the battery to the genset, first with positive pole, then with negative pole
  4. Start diesel genset from the controller
  5. Check the abnormal noise or vibration of the genset
  6. Check if there is leakage problem for the three liquids (coolant, fuel and oil) & air exhaust system have leakage phenomenon.
  7. Check if there is any unusual indication on the meter of control system.
  8. Check the output voltage and frequency from the control screen
  9. Every starting, stopping or one hour running, record the operating parameter of the genset one time.
  10. Keep the load of genset without exceeding rated value.
  11. Check whether the gensets can start automatically after get a signal from ATS.
  12. Start the synchronization function once the gensets are working smoothly.